Many of you have been asking about the progress of our new Parish Center and how it is coming along. The number one question has been “when will it be done”? As of now, we are projected to move in around the first of the year. We have battled a bit of weather in recent weeks, but with the early start courtesy of the nice weather, we are only slightly behind schedule. The good news is that there are no delays at this time with getting materials delivered on time. So far, we have poured the footings and the foundation walls and will soon be backfilling walls and pouring the elevator pit. Every few weeks, we will put out an update to keep you apprised of how the project is going. Please pray for the safety of all our workers and for good weather!